Procedure to start the Entra Connect server from staging and decommissioning the old Azure AD connect server

EnterpriseArchitect 5,036 Reputation points
2024-03-13T11:29:45.7366667+00:00

What are the actions I need to take to complete the following process?

  1. Stop the old Azure AD Connect server in production.
  2. Launch the new Azure AD Connect / Entra Connect staging server into production.
  3. Shut down and decommission the previous Azure AD connect server from both OnPremise and Azure AD/Entra ID.

Your help is greatly appreciated. Thank you in advance!

Active Directory
Active Directory
A set of directory-based technologies included in Windows Server.
6,154 questions
Microsoft Exchange Hybrid Management
Microsoft Exchange Hybrid Management
Microsoft Exchange: Microsoft messaging and collaboration software.Hybrid Management: Organizing, handling, directing or controlling hybrid deployments.
1,980 questions
Windows Server Security
Windows Server Security
Windows Server: A family of Microsoft server operating systems that support enterprise-level management, data storage, applications, and communications.Security: The precautions taken to guard against crime, attack, sabotage, espionage, or another threat.
1,775 questions
Microsoft Entra
Microsoft Entra ID
Microsoft Entra ID
A Microsoft Entra identity service that provides identity management and access control capabilities. Replaces Azure Active Directory.
20,397 questions
{count} votes

Accepted answer
  1. Marcin Policht 16,965 Reputation points MVP
    2024-03-13T11:32:35.3333333+00:00

    The procedure is the same one that you'd follow to replace an active instance of Entra Connect Sync with a staging one. Detailed step by step instructions are available at https://video2.skills-academy.com/en-us/entra/identity/hybrid/connect/how-to-connect-sync-staging-server


    hth

    Marcin

    1 person found this answer helpful.

1 additional answer

Sort by: Most helpful
  1. Thameur-BOURBITA 32,621 Reputation points
    2024-03-13T13:48:19.9866667+00:00

    Hi @EnterpriseArchitect

    You should follow these steps:

    1. Install and configure staging mode new server using the exported configuration from old server: Install Microsoft Entra Connect with staging mode
    2. Enable staging mode on old server : Change currently Active Sync Server to staging mode
    3. Disable staging mode on new server: you can use the same procedure in previous steps but you have to uncheck this option :
      Screenshot shows Staging Mode configuration in the Active Microsoft Entra Connect dialog box.
    4. If the synchronisation works well , you can stop and decom old server

    Please don't forget to accept helpful answer