Refresh Planning Demand Batch Job

Refreshes the BOM and the routing for the selected planning worksheet line or order planning line using the latest master data.

Use this batch job when you have made small changes in the planning worksheet or Order Planning window. For example, use it if you have changed an assigned routing or an assigned BOM for a line or want to add another planning worksheet line or order planning line to an existing run. The batch job then deletes the components and routings of the planning lines in question and forms new component lines and routings on the basis of standard data.

Options

Scheduling direction: Enter the scheduling method - forward or backward.

Forward scheduling begins at the starting date and proceeds forward to the finishing date. Backward scheduling begins from the ending date and proceeds backward to the required starting date.

Calculate:

Routings: Click to insert a check mark in the check box if you want the program to refresh the routing.

Component Need: Click to insert a check mark in the check box if you want the program to recalculate the BOM.

Tip

For more information on how to work with batch jobs, see How to: Run Batch Jobs and How to: Set Filters. For assistance in finding specific pages, see Search.