Sequence No. (Forward) Field, Prod. Order Routing Line Table
Specifies the sequence number (forward).
It is possible to plan a production order by forward and backward calculation. Depending on the planning, sequence numbers are assigned. Here the sequence number is entered which this operation has in the forward planning.
Example:
OP1 |
OP2 |
OP3 |
OP4 |
OP5 |
OP6 |
1 |
2 |
3 |
4 |
5 |
6 |
*OP stands for operation - the numbers in the line below correspond to the sequence number in the forward calculation.
To see the difference between forward and backward calculation in the range of sequence numbers, click here.