Task.FixedCostAccrual Enumeration
Specifies how and when fixed costs are to be charged to the cost of a task.
Namespace: Microsoft.Office.Project.Server.Library
Assembly: Microsoft.Office.Project.Server.Library (in Microsoft.Office.Project.Server.Library.dll)
Syntax
'Declaration
Public Enumeration FixedCostAccrual
'Usage
Dim instance As Task.FixedCostAccrual
public enum FixedCostAccrual
Members
Member name | Description | |
---|---|---|
Start | Value=1. Costs are accrued as soon as the task starts. A task begins when a date is entered in the ActualStart field. | |
Prorated | Value=2. Costs accrue as work is scheduled to occur and as actual work is reported. This is the default value. | |
End | Value=3. Costs are not accrued until the remaining work is zero. |
Remarks
Use the Task.FixedCostAccrual type to set the TASK_FIXED_COST_ACCRUAL property in the following objects: