ProjectDataSet.TaskRow.TASK_EAC Property

Estimate at completion is the total scheduled or projected cost for the task based on costs already incurred, in addition to the costs planned for remaining work.

Namespace:  [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl

Syntax

'Declaration
Public Property TASK_EAC As Double
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Double

value = instance.TASK_EAC

instance.TASK_EAC = value
public double TASK_EAC { get; set; }

Property Value

Type: System.Double

Remarks

Read-only.

TASK_EAC = TB_ACWP() + (TB_COST X - TASK_BCWP) / TASK_CPI

See Also

Reference

ProjectDataSet.TaskRow Class

ProjectDataSet.TaskRow Members

Project Web Service