ProjectDataSet.TaskRow.TASK_EARLY_START Property

Specifies the earliest possible date the task can start.

Namespace:  [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl

Syntax

'Declaration
Public Property TASK_EARLY_START As DateTime
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As DateTime

value = instance.TASK_EARLY_START

instance.TASK_EARLY_START = value
public DateTime TASK_EARLY_START { get; set; }

Property Value

Type: System.DateTime

Remarks

Read-only. The earliest date that the task could possibly begin, based on the early start dates of predecessor and successor tasks, and other constraints.

See Also

Reference

ProjectDataSet.TaskRow Class

ProjectDataSet.TaskRow Members

Project Web Service