ProjectDataSet.TaskRow.TASK_IS_MANUAL property

Gets or sets the Boolean value that specifies whether the task is scheduled manually or automatically. True if manually scheduled.

Namespace:  WebSvcProject
Assembly:  ProjectServerServices (in ProjectServerServices.dll)

Syntax

'Declaration
Public Property TASK_IS_MANUAL As Boolean
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Boolean

value = instance.TASK_IS_MANUAL

instance.TASK_IS_MANUAL = value
public bool TASK_IS_MANUAL { get; set; }

Property value

Type: System.Boolean

Remarks

When you change an automatically scheduled task to be manually scheduled, Project Server maintains the TASK_START_DATE, TASK_FINISH_DATE, and related properties that the scheduling engine last calculated for the task. If a manually scheduled task is changed to automatically scheduled, the scheduling engine can change the dates, based on other factors such as calendars and constraints.