ProjectDataSet.TaskRow.TASK_IS_MANUAL property
Gets or sets the Boolean value that specifies whether the task is scheduled manually or automatically. True if manually scheduled.
Namespace: WebSvcProject
Assembly: ProjectServerServices (in ProjectServerServices.dll)
Syntax
'Declaration
Public Property TASK_IS_MANUAL As Boolean
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Boolean
value = instance.TASK_IS_MANUAL
instance.TASK_IS_MANUAL = value
public bool TASK_IS_MANUAL { get; set; }
Property value
Type: System.Boolean
Remarks
When you change an automatically scheduled task to be manually scheduled, Project Server maintains the TASK_START_DATE, TASK_FINISH_DATE, and related properties that the scheduling engine last calculated for the task. If a manually scheduled task is changed to automatically scheduled, the scheduling engine can change the dates, based on other factors such as calendars and constraints.