TrackingMode enumeration
Specifies the modes for tracking task progress.
Namespace: Microsoft.ProjectServer.Client
Assembly: Microsoft.ProjectServer.Client (in Microsoft.ProjectServer.Client.dll)
Syntax
'Declaration
Public Enumeration TrackingMode
'Usage
Dim instance As TrackingMode
public enum TrackingMode
Members
Member name | Description | |
---|---|---|
None | Value=0. Use free-form tracking for tasks, where resources can report hours by using any method (actual hours, percent complete, or timephased). | |
TimePhased | Value=1. Use timephased tracking for tasks, by hours of work done per period. | |
PercentComplete | Value=2. Track tasks by percentage of work complete. | |
ActualHours | Value=3. Track tasks by actual hours of work done and work remaining. |
Remarks
You can set the tracking mode in the Tracking Method section of the Task Settings and Display page in Project Web App (http://ServerName/ProjectServerName/_layouts/15/pwa/Admin/Statusing.aspx).