Your organization is based in Georgia, US, and has expanded its operations to include a new production line in California, US. You've added the new employees as project resources in Project Operations. You need to change the schedule of these employees because they are in different time zones. How can you complete this task most efficiently?
Modify the working time for each new employee.
Nothing, because Project Operations is location-aware of the new employees.
Create a new project calendar template, and assign it to the new employees
Have the administrator modify the time zone for each employee in Advanced Settings > System > Security > Users.
Which resource type isn't valid in Project Operations?
Crew
Team
Pool
Equipment
You're a resource manager who works at Fabrikam. The organization has configured the resource management mode as hybrid. You receive a call from one of the project managers, who is upset that a crucial named resource who was originally assigned to their project plan has been allocated to another project manager. What caused the problem?
The resource manager made a mistake.
The project manager didn't soft book the resource.
The project manager didn't hard book the resource.
The schedule assistant is broken.