Knowledge check

Completed

Choose the best response for each of the questions.

Check your knowledge

1.

When initiating a project to deploy an SAP workload to Azure, which of the following tasks is part of the project preparation and planning phase in the SAP workload planning and deployment checklist?

2.

The following is a list of some of the steps in the pilot phase of deploying an SAP workload to Azure using the SAP workload planning and deployment checklist. 1. Optimize data transfer into Azure. 2. Test and optimize export and import phases. 3. Perform technical validation. 4. Test performance. Which step is missing?

3.

What is the last step that should be carried out when an SAP workload has just reached the Go Live stage of its deployment to Azure, if there are other SAP systems that weren't part of the current Go Live phase, but which communicate with the deployed workload?