ProjectDataSet.TaskRow.TASK_ACT_WORK Property
Specifies the amount of work that has been done by the resources that are assigned to the task.
Namespace: [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl
Syntax
'Declaration
Public Property TASK_ACT_WORK As Double
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Double
value = instance.TASK_ACT_WORK
instance.TASK_ACT_WORK = value
public double TASK_ACT_WORK { get; set; }
Property Value
Type: System.Double
Remarks
TASK_ACT_WORK is a calculated field.
Work is stored as thousandths of a minute. For example, a value of 10000 indicates 10 minutes.