Prod. Order Capacity Need Window

Specifies the time that is needed to complete the production order.

The capacity that is needed for each order is the sum of the setup time and the run time. The run time is equal to the run time per piece multiplied by the number of pieces in the order.

The production order capacity need is calculated when you run the Refresh Production Order batch job. For more information, see How to: Refresh Production Orders.

Tip

For more information on how to navigate in the user interface, see Work with Microsoft Dynamics NAV. For assistance in finding specific pages, see Search.

See Also

Reference

Allocated Capacity Need
Production Order Statistics

Other Resources

Refresh Production Order
Structure of the Capacity