ProjectDataSet.TaskRow.TASK_REM_WORK Property

Task remaining work contains the amount of time required to complete the task.

Namespace:  [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl

Syntax

'Declaration
Public Property TASK_REM_WORK As Double
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Double

value = instance.TASK_REM_WORK

instance.TASK_REM_WORK = value
public double TASK_REM_WORK { get; set; }

Property Value

Type: System.Double

Remarks

TASK_REM_WORK = TASK_WORK - TASK_ACT_WORK

Work is stored as thousandths of a minute. For example, 10000 indicates 10 minutes.