ProjectDataSet.TaskRow.TASK_EARLY_FINISH Property
Specifies the earliest possible date on which the task can finish.
Namespace: [Statusing Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Statusing.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Statusing.asmx?wsdl
Syntax
'Declaration
Public Property TASK_EARLY_FINISH As DateTime
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As DateTime
value = instance.TASK_EARLY_FINISH
instance.TASK_EARLY_FINISH = value
public DateTime TASK_EARLY_FINISH { get; set; }
Property Value
Type: System.DateTime
Remarks
Read-only. The earliest date that a task can possibly finish, based on early finish dates of predecessor tasks and successor tasks, other constraints, and any leveling delay.