ProjectDataSet.TaskRow.TASK_OVT_WORK Property
Specifies the total amount of overtime work on a task.
Namespace: [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl
Syntax
'Declaration
Public Property TASK_OVT_WORK As Double
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Double
value = instance.TASK_OVT_WORK
instance.TASK_OVT_WORK = value
public double TASK_OVT_WORK { get; set; }
Property Value
Type: System.Double
Remarks
Read-only. When a task is created, TASK_OVT_WORK shows 0 hrs. When you enter scheduled overtime work in the sheet portion of the Task Usage view or Resource Usage view for the assignment, Project Professional rolls up the overtime work hours and calculates the total overtime work for the task.
Work is stored as thousandths of a minute. For example, 10000 indicates 10 minutes.