ProjectDataSet.TaskRow.TASK_FINISH_DATE Property

The date when this task is scheduled to be completed.

Namespace:  [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl

Syntax

'Declaration
Public Property TASK_FINISH_DATE As DateTime
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As DateTime

value = instance.TASK_FINISH_DATE

instance.TASK_FINISH_DATE = value
public DateTime TASK_FINISH_DATE { get; set; }

Property Value

Type: System.DateTime

Remarks

Read-only, except when the task is created. The Project Server scheduling engine calculates the finish date based on the start date, task duration, task dependencies, the project calendar, and other task constraints. If resources are assigned, the scheduling engine also considers the resource calendar and assignment units. For more information, see Task Start and Finish Dates.

See Also

Reference

ProjectDataSet.TaskRow Class

ProjectDataSet.TaskRow Members

Project Web Service