The following fields track information about bugs, issues, and risks. These work item types are defined within the process template for Microsoft Solutions Framework (MSF) CMMI Process Improvement.
Bug tracking fields
These fields are neither reported nor indexed:
Field name |
Description |
Reference name |
Data type |
---|---|---|---|
Symptom |
The unexpected behavior. |
Microsoft.VSTS.CMMI.Symptom |
HTML |
Proposed Fix |
The proposed change to fix the reported problem. |
Microsoft.VSTS.CMMI.ProposedFix |
HTML |
Found in Environment |
The software setup and configuration where the bug was found. |
Microsoft.VSTS.CMMI.FoundInEnvironment |
String |
Root Cause |
The cause of the error. You can specify one of the following values:
To change the menu selection, see Customize a pick list. |
Microsoft.VSTS.CMMI.RootCause |
String |
How Found |
How the bug was found. For example, a bug might have been found during a customer review or through ad hoc testing. |
Microsoft.VSTS.CMMI.HowFound |
String |
Issue tracking fields
These fields are not indexed:
Field name |
Description |
Reference name |
Data type |
Default value of the reportable type attribute |
---|---|---|---|---|
Analysis |
The root cause of the issue and one or more solutions that might resolve it. |
Microsoft.VSTS.CMMI.Analysis |
HTML |
None |
Corrective Action Actual Resolution |
What the team actually did to correct the issue. |
Microsoft.VSTS.CMMI.CorrectiveActionActualResolution |
HTML |
None |
Corrective Action Plan |
The proposed corrective action on which the team has agreed. |
Microsoft.VSTS.CMMI.CorrectiveActionPlan |
HTML |
None |
Target Resolve Date |
The date when the issue becomes critical and starts to affect the critical path of the project plan. |
Microsoft.VSTS.CMMI.TargetResolveDate |
DateTime |
None |
Risk tracking fields
These fields are neither reported nor indexed:
Field name |
Description |
Reference name |
Data type |
---|---|---|---|
Contingency Plan |
The actions to take if the risk occurs. You can create and link tasks to the Risk work item to track the work that the team must complete to implement the contingency plan. Also, you can create an Issue work item to track one or more issues on which the risk has an impact. |
Microsoft.VSTS.CMMI.ContingencyPlan |
HTML |
Mitigation Plan |
The actions to take to reduce the probability or impact of the risk. You can create and link tasks to the Risk work item to track the work that the team must complete to implement the mitigation plan. |
Microsoft.VSTS.CMMI.MitigationPlan |
HTML |
Mitigation Triggers |
The conditions or events that determine how the team might mitigate a risk. For example, the triage team might authorize and obtain a reserve generator if the weather forecast is predicting an ice storm or hurricane to hit within 50 miles of the office within the next four days. |
Microsoft.VSTS.CMMI.MitigationTriggers |
HTML |
Probability |
A number that indicates the chance that the risk will occur. A valid probability number is between 1 and 99, where 99 indicates that the risk is almost certain to occur. |
Microsoft.VSTS.CMMI.Probability |
Integer |