LoadGen Server Stress - Start Test for Fault Tolerant Server
This automated test measures the stress load on a fault tolerant server. This test does the following:
Copies test files to the Master Client.
Runs the test on the Master Client.
Copies the test logs after the test finishes.
Test details
Associated requirements |
System.Server.FaultTolerant.Core |
Platforms |
Windows Server 2012 (x64) Windows Server 2008 R2 (x64) Windows Server 2012 R2 |
Expected run time |
~1440 minutes |
Categories |
Certification |
Type |
Automated |
Running the test
Before you run the test:
Verify the test setup as described in the test requirements: System Server Testing Prerequisites and Test Server Configuration.
Run LoadGen Server Stress - Run First - Set Machine Policies first, to setup the correct machine policy settings.
From HCK Studio, select and run test.
Troubleshooting
For troubleshooting information, see Troubleshooting System Server Testing.