How to: Recalculate Calendar Entries for Work Centers

You can update the calendar entries after changes in the shop calendar. The existing calendar entries are validated to make sure they correspond to the shop calendar. The appropriate calendar entry is corrected if deviations are determined.

To recalculate calendar entries for work a center

  1. In the Search box, enter Work Centers, and then choose the related link.

  2. Open the relevant work center from the list.

  3. On the Navigate tab, in the Planning group, choose Calendar.

  4. In the Work Center Calendar window, choose Show Matrix.

  5. In the Work Center Calendar Matrix window, select the calendar or calendars that you want to calculate.

  6. On the Actions tab, In the Functions group, choose Calculate.

  7. Set filters to define which calendar period to calculate, and then choose the OK button.

Important

The recalculation of calendar entries overwrites any manual changes made to the calendar entries. Only existing calendar entries of the work center are validated, therefore, the function cannot create new calendar entries.

See Also

Tasks

How to: Recalculate Calendar Entries for Machine Centers
How to: Enter Time Periods When Work Centers Cannot Be Used
How to: Update Calendar Entries for Work Centers
How to: Create Work Center Calendars

Concepts

Shop Calendars