Next Operation No. Field, Routing Line Table
Specifies the next operation number. You use this field if you use parallel routings.
If you do not use parallel routings, it is not necessary to set up any number in this field. The program automatically takes the operations in sequence.
By entering the next operation number, you determine the order of the processing steps.
Example:
After operation 10, the next sequential operation number (for example 20) must not follow automatically, but operation 30 or two parallel operations, for example 20 and 30, must follow.
You can enter a number (for example 30) or a number range (for example 20 to 30 - 20..30) or a combination of numbers (for example 20 and 40 - 20|40).