ProjectDataSet.TaskRow.TASK_START_SLACK Property
Specifies the amount of time that the start date for the specified task can be delayed without delaying the project.
Namespace: [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl
Syntax
'Declaration
Public Property TASK_START_SLACK As Integer
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Integer
value = instance.TASK_START_SLACK
instance.TASK_START_SLACK = value
public int TASK_START_SLACK { get; set; }
Property Value
Type: System.Int32
Remarks
The TASK_START_SLACK field contains the duration between the TASK_EARLY_START and TASK_LATE_START.
The duration is indicated in tenths of minutes. A value of 100 indicates 10 minutes.